DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT |
TAHUN ANGGARAN 2020 |
| | | | | | | | | |
Bidang | : | Pelaksanaan Pembangunan Desa (2) |
Sub Bidang | : | Kawasan Permukiman (2.4.) |
Kegiatan | : | Pembangunan Sambungan Air Bersih ke Rumah Tangga (Pipanisasi) (2.4.12.) |
Paket Kegiatan | : | Pembangunan Broncaptering dan Pipanisasi Sepanjang 2.142 meter |
Waktu Pelaksanaan | : | 60 (enam puluh hari kalender) |
| | | | | | | | | |
Rincian Pendanaan | : | | | | | | |
NO. | U R A I A N | VOLUME | | HARGA SATUAN (Rp) | JUMLAH (Rp) |
1 | 2 | 3 | 4 | 5 |
I. | | BAHAN | | | | | |
| | Broncaptering (1 unit): | | | | | |
| 1 | Semen @ 50 Kg | 79.00 | Zak | | 110,000.00 | 8,690,000.00 |
| 2 | Batu 2/3 | 9.00 | M3 | | 350,000.00 | 3,150,000.00 |
| 3 | Pasir Beton | 8.00 | M3 | | 355,000.00 | 2,840,000.00 |
| 4 | Besi � 8 mm - 12 m | 63.00 | Btg | | 58,000.00 | 3,654,000.00 |
| 5 | Kawat Ikat | 6.00 | Kg | | 22,000.00 | 132,000.00 |
| 6 | Papan Mal | 48.00 | Kpg | | 30,000.00 | 1,440,000.00 |
| 7 | Paku Campur | 3.00 | Kg | | 23,000.00 | 69,000.00 |
| 8 | Pipa Saringan Besi � 4" | 1.00 | Bh | | 1,455,000.00 | 1,455,000.00 |
| 9 | Pipa Bilas 3"-4m | 1.00 | Bh | | 125,000.00 | 125,000.00 |
| | Perpipaan (2.142 meter): | | | | | |
| 10 | Pipa Besi (Galvanis) � 4"-6m | 1.00 | Btg | | 1,750,000.00 | 1,750,000.00 |
| 11 | Pipa PVC AW � 4"-6 m | 30.00 | Btg | | 405,000.00 | 12,150,000.00 |
| 12 | Pipa PVC AW � 3"-6 m | 50.00 | Btg | | 295,000.00 | 14,750,000.00 |
| 13 | Pipa PVC AW � 2"-6 m | 277.00 | Btg | | 165,000.00 | 45,705,000.00 |
| 14 | Reduser 4" ke 3" | 1.00 | Bh | | 180,000.00 | 180,000.00 |
| 15 | Reduser 3" ke 2" | 1.00 | Bh | | 132,000.00 | 132,000.00 |
| 16 | Reduser 2" ke 1" | 1.00 | Bh | | 75,000.00 | 75,000.00 |
| 17 | Stop Kran ( Gate Valve) 4" | 1.00 | Bh | | 1,150,000.00 | 1,150,000.00 |
| 18 | Lem Pipa | 7.00 | Kg | | 30,000.00 | 210,000.00 |
| | Tandon Air (1 unit): | | | | | |
| 19 | Kayu Belian 9/9 - 4 m | 2.00 | Btg | | 200,000.00 | 400,000.00 |
| 20 | Kayu Belian 4/9 - 4 m | 7.00 | Btg | | 100,000.00 | 700,000.00 |
| 21 | Kayu Belian 7/7 - 4 m | 1.00 | Btg | | 190,000.00 | 190,000.00 |
| 22 | Kayu Belian 4/6 - 4 m | 2.00 | Btg | | 90,000.00 | 180,000.00 |
| 23 | Papan Belian | 3.00 | Kpg | | 130,000.00 | 390,000.00 |
| 24 | Paku Belian | 1.00 | Kg | | 33,000.00 | 33,000.00 |
| 25 | Fiberglass 1.500 Ltr (setara Penguin) | 1.00 | Bh | | 1,800,000.00 | 1,800,000.00 |
| 26 | Pipa PVC AW � 3/4" - 4 m | 2.00 | Btg | | 40,000.00 | 80,000.00 |
| 27 | Baut | 24.00 | Bh | | 10,000.00 | 240,000.00 |
| 28 | Stop Kran 3/4" | 1.00 | Bh | | 20,000.00 | 20,000.00 |
| 29 | Lem Pipa | 1.00 | Klg | | 30,000.00 | 30,000.00 |
| | Kran Umum (4 unit) | | | | | |
| 30 | Besi dia. 8 - 12 m | 2.00 | Btg | | 58,000.00 | 116,000.00 |
| 31 | Kawat Ikat | 1.00 | Kg | | 22,000.00 | 22,000.00 |
| 32 | Papan Mal | 1.00 | Kpg | | 30,000.00 | 30,000.00 |
| 33 | Paku Campur | 1.00 | Kg | | 23,000.00 | 23,000.00 |
| 34 | Semen @ 50 Kg | 5.00 | Zak | | 110,000.00 | 550,000.00 |
| 35 | Batu uk. 2/3 | 1.00 | M3 | | 350,000.00 | 350,000.00 |
| 36 | Pasir Beton | 1.00 | M3 | | 355,000.00 | 355,000.00 |
| 37 | Kran Stop 3/4" | 8.00 | Bh | | 20,000.00 | 160,000.00 |
| 38 | Pipa PVC AW 3/4"-4m | 2.00 | Btg | | 40,000.00 | 80,000.00 |
| 39 | T - Bow 3/4" | 4.00 | Bh | | 15,000.00 | 60,000.00 |
| 40 | L - Bow 3/4" | 4.00 | Bh | | 11,000.00 | 44,000.00 |
| 41 | Sealtape | 2.00 | Bh | | 5,000.00 | 10,000.00 |
| 42 | Lem Pipa | 1.00 | Klg | | 30,000.00 | 30,000.00 |
| | | | | | | |
| | | | | | | | | |
| | | | | | | Jumlah Bahan | 103,550,000.00 |
| | | | | | | | | |
II. | | SEWA ALAT (sesuai keperluan) | | | | | |
| 1. | Gerobak Dorong | 2.00 | Bh | | 200,000.00 | 400,000.00 |
| | | | | | | | | |
| | | | | | | Jumlah Alat | 400,000.00 |
| | | | | | | | | |
III. | | UPAH | | | | | |
| 1. | Pekerja | 204.80 | HOK | | 85,000.00 | 17,408,000.00 |
| 2. | Tukang | 98.00 | HOK | | 120,000.00 | 11,760,000.00 |
| 3. | Kepala Tukang | 41.20 | HOK | | 140,000.00 | 5,768,000.00 |
| 4. | Mandor | 20.00 | HOK | | 120,000.00 | 2,400,000.00 |
| | | | | | | | | |
| | | | | 364.00 | HOK | Jumlah Upah | 37,336,000.00 |
IV. | | HONOR TPK | | | | | |
| 1. | Ketua | 1.00 | org | | 450,000.00 | 450,000.00 |
| 2. | Sekretaris | 1.00 | org | | 400,000.00 | 400,000.00 |
| 3. | Anggota | 2.00 | org | | 350,000.00 | 700,000.00 |
| | (Perbup Sanggau No. 1 Thn. 2019) | | | | | |
| | | | | | | | | |
| | | | | 4.00 | org | Jumlah Honor TPK | 1,550,000.00 |
| | | | | | | | | |
| | | | | | | | | |
J U M L A H (Rp.) | | | | | 142,836,000.00 |
| | | | | | | | | |
| | | | | | | | Pasir Bedengung, 5 Februari 2020 |
| | | | | | | | | |
Disetujui : | | |
Kepala Desa Pasir Bedengung | | Kasi Kesejahteraan |
| | | | | | | | | |
| | | | | | | | |
Bunga Citra Lovestory, SH. | | | Ramlee |