Desain dan RAB Jembatan Gantung Bentang 51 Meter


 









RENCANA  ANGGARAN  BIAYA (RAB)
DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT
TAHUN ANGGARAN 2020
Bidang  : Pelaksanaan Pembangunan Desa (2)
Sub Bidang  : Pekerjaan Umum dan Penataan Ruang (2.3.)
Kegiatan  : Pembangunan Jembatan Milik Desa (2.3.13.)
Pembangunan Jembatan Gantung RT. 1 RW. 2 Dusun Bahagia ukuran 51 m x 1,5 m
Waktu Pelaksanaan  : 90 (sembilan puluh hari kalender)
Rincian Pendanaan  :
NO. U  R  A  I  A  N VOLUME HARGA SATUAN  (Rp) JUMLAH (Rp)
1 2 3 4 5
I. BAHAN (harga hanya contoh)
1 Semen (@ 50 Kg) 345 Zak 120,000 41,400,000.00
2 Pasir Beton 27 M3 150,000 4,050,000.00
3 Batu Pecah uk. 2/3  42 M3 150,000 6,300,000.00
4 Kabel (sling) Utama � 1 inci  208 M' 150,000 31,200,000.00
5 Kabel (sling) Pengaku � 3/4 inci  74 M' 110,000 8,140,000.00
6 Besi Penggantung � 16 mm 18 btg 190,000 3,420,000.00
7 Stel drat besi penggantung 66 btg 35,000 2,310,000.00
8 Cekak ukuran 1 inci 32 bh 35,000 1,120,000.00
9 Cekak ukuran 3/4 inci 32 bh 28,000 896,000.00
10 Warfel ukuran 1 inci 4 bh 350,000 1,400,000.00
11 Warfel ukuran 3/4 inci 4 bh 250,000 1,000,000.00
12 Roller Kabel Baja 4 set 800,000 3,200,000.00
13 Besi Angker utama � 38 mm  2 btg 2,250,000 4,500,000.00
14 Besi Angker pengaku � 25 mm  4 btg 625,000 2,500,000.00
15 Plat Gantung 4x100x150 mm  66 set 105,000 6,930,000.00
16 Plat Kait Keep 4x40x80 mm  132 btg 40,000 5,280,000.00
17 Plat Tiang Pilon 4.50.500 24 btg 75,000 1,800,000.00
18 Besi Polos � 12 mm 151 btg 130,000 19,630,000.00
19 Besi Polos � 10 mm 7 btg 110,000 770,000.00
20 Kayu Belian 15/15 - 4 M 40 btg 1,700,000.00 68,000,000.00
21 Kayu Belian 7/15 - 4M  71 btg 800,000.00 56,800,000.00
22 Kayu Belian 9/9 - 4M  121 btg 360,000.00 43,560,000.00
23 Kayu Belian 8/8 - 4M  64 btg 210,000.00 13,440,000.00
24 Kayu Belian 4/8 - 4M  122 btg 120,000.00 14,640,000.00
25 Papan Belian  3/15 - 2 M 452 kpg 175,000.00 79,100,000.00
26 Mur Baut � 3/8" x 1,5" 132 set 3,000 396,000.00
27 Mur Baut � 3/8" x 8" 302 set 15,000 4,530,000.00
28 Mur Baut � 3/8" x 12" 90 bh 25,000 2,250,000.00
29 Mur Baut � 5/8" x 2,5" 66 set 5,000 330,000.00
30 Mur Baut � 5/8" x 8" 36 set 20,000 720,000.00
31 Mur Baut � 5/8" x 11" 72 set 35,000 2,520,000.00
32 Mur Baut � 5/8" x 14" 64 set 45,000 2,880,000.00
33 Mur  � 5/8"  132 set 1,500 198,000.00
34 Paku Belian (campur) 130 kg 30,000 3,900,000.00
35 Paku Biasa (campur) 57 kg 28,000 1,596,000.00
36 Cat Kilat 48 kg 50,000 2,400,000.00
37 Minyak Cat 10 kg 25,000 250,000.00
38 Amplas 19 lbr 5,000 95,000.00
39 Teer 44 kg 20,000 880,000.00
40 Papan Mal Kayu Klas III uk. 3/18-4m 132 kpg 30,000 3,960,000.00
41 Kayu Klas III uk. 5/7-4m 60 btg 20,000 1,200,000.00
42 Kayu bulat (u/ perancah) � 10cm-4m 134 btg 17,000 2,278,000.00
Jumlah Bahan 451,769,000.00
II. SEWA ALAT  (sesuai keperluan)
1. Gerobak Dorong 4.00 Bh 200,000.00 800,000.00
2. Concrete mixer (molen) & operasional 11.00 hari 400,000.00 4,400,000.00
Jumlah Alat 5,200,000.00
III. UPAH
1. Pekerja 347.00 HOK 85,000.00 29,495,000.00
2. Tukang  288.00 HOK 120,000.00 34,560,000.00
3. Kepala Tukang 44.00 HOK 140,000.00 6,160,000.00
4. Mandor 30.00 HOK 120,000.00 3,600,000.00
700.00 HOK Jumlah Upah 73,815,000.00
IV. HONOR TPK 
1. Ketua 2.00 OK 500,000.00 1,000,000.00
2. Sekretaris 2.00 OK 450,000.00 900,000.00
3. Anggota 6.00 OK 340,000.00 2,040,000.00
(Perbup Sanggau No. 1 Thn. 2019)
10.00 OK Jumlah Honor TPK 3,940,000.00
J  U  M  L  A  H  (Rp.) 534,724,000.00
Pasir Bedengung, 6 Februari 2020
Disetujui :
Kepala Desa Pasir Bedengung Kasi Kesejahteraan
Bunga Citra Lovestory, SH. Ramlee